MISSION LOG
Proven operational performance across utility-scale monopile and jacket piling campaigns. From initial prototype trials to high-capacity electrified spreads, our hardware track record is defined by raw operational uptime and deployment precision.
Scroll to explore ↓
>6,000 MW OF POWER
>700 WIND TURBINES
>30,000 m BBC

> CASE_STUDY // BOSKALIS_US_PORTFOLIO
---------------------------------
CLIENT : BOSKALIS
DEVELOPER/OPER : ØRSTED
PROJECT_SPREAD : SOUTH FORK WIND | REVOLUTION WIND | SUNRISE WIND
TIMELINE : 2023 - 2025
VOLUME_SCOPE : > 160 MONOPILES INSTALLED
SERVICE_SCOPE : FAR FIELD NOISE MITIGATION
---------------------------------
[DBBC]STATUS: MISSION COMPLETE // 100% REGULATORY COMPLIANCE

> CASE_STUDY // TPC_PHASE_II_TAIWAN
---------------------------------
CLIENT : FOXWELL ENERGY
DEVELOPER/OPER : TAIWAN POWER COMPANY (TPC)
PROJECT_SPREAD : TPC PHASE II OFFSHORE WIND FARM
TIMELINE : 2024 - 2025
VOLUME_SCOPE : 31 JACKET FOUNDATIONS (300 MW)
SERVICE_SCOPE : FAR FIELD NOISE MITIGATION [DBBC]
---------------------------------
STATUS: MISSION COMPLETE // 100% REGULATORY COMPLIANCE

> CASE_STUDY // EXTREME_WATER_DEPTH
---------------------------------
CLIENT : EUROPEAN INFRASTRUCTURE DEVELOPER
OPERATOR : GLOBAL OFFSHORE WIND OPERATOR
PROJECT_SPREAD: 87 ACTIVE CLEARANCE LOCATIONS
TIMELINE : 2018
ENVIRONMENT : EXTREME WATER DEPTH (UP TO -88.4M)
SERVICE_SCOPE : BIG BUBBLE CURTAIN (BBC) DEPLOYMENT
---------------------------------
[BBC]STATUS: MISSION COMPLETE // 100% BSH COMPLIANCE
OPERATIONAL TIMELINE
Tracking the evolution of subsea noise mitigation: beginning with 2011 nearfield isolation prototypes (ESRa) and scaling into electrified, zero-emission acoustic spreads for next-generation offshore wind foundations.
ESRa - R&D Project
> TRACK_RECORD // 2011_ESRA
// RESEARCH_AND_DEVELOPMENT
---------------------------------------
PROJECT : ESRa
YEAR : 2011
SCOPE : Underwater Noise Mitigation Research Project
HARDWARE : Small Bubble Curtain, BEKA Shell
---------------------------------------
STATUS: COMPLETED // RESEARCH DATA ARCHIVED
2011
RWE NSO Wind Farm
> TRACK_RECORD // 2011_ESRA
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : RWE NSO Wind Farm
YEAR : 2011
SCOPE : Offshore Wind Farm
HARDWARE : Double Big Bubble Curtain
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
2013
DanTysk Wind Farm
> TRACK_RECORD // 2013_DANTYSK
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : ESRa
YEAR : 2013
SCOPE : Offshore Wind Farm - 80 Monopiles
HARDWARE : DBBC, TBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
2014
Amrumbank West
> TRACK_RECORD // 2014_AMRUMBANK_WEST
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : Amrumbank West
YEAR : 2014
SCOPE : Offshore Wind Farm - 88 Monopiles
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
2015
SylWin Alpha
> TRACK_RECORD // 2015_SYLWIN_ALPHA
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : SylWin Alpha
YEAR : 2015
SCOPE : Offshore Wind Far
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
UXO Projects North Sea
2016
Veja Mate Wind Farm
> TRACK_RECORD // 2016_VEJA_MATE
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : Veja Mate Wind Farm
YEAR : 2016
SCOPE : Offshore Wind Farm - 30 Monopiles
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
Sandbank OSS
> TRACK_RECORD // 2016_SANDBANK_OSS
// SUBSTATION_INSTALLATION
---------------------------------------
PROJECT : Sandbank OSS
YEAR : 2016
SCOPE : Offshore Substation
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
DolWin
> TRACK_RECORD // 2016_DOLWIN
// SUBSTATION_INSTALLATION
---------------------------------------
PROJECT : DolWin
YEAR : 2016
SCOPE : Offshore Substation
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
2018
Nord Stream II
> TRACK_RECORD // 2018_NORD_STREAM_II
// DETONATION_MITIGATION
---------------------------------------
PROJECT : Nord Stream II
YEAR : 2018
SCOPE : UXO Clearance
HARDWARE : SBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
Borselle Substation
UXO Project North Sea
2019
Deutsche Bucht
> TRACK_RECORD // 2019_DEUTCSCHE_BUCHT
// SUBSTATION_INSTALLATION
---------------------------------------
PROJECT : Deutsche Bucht
YEAR : 2019
SCOPE : Offshore Substation
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
Borssele Beta
> TRACK_RECORD // 2019_BORSSELE_BETA
// SUBSTATION_INSTALLATION
---------------------------------------
PROJECT : Borssele Beta
YEAR : 2019
SCOPE : Offshore Substation
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
Formosa
> TRACK_RECORD // 2019_FORMOSA_1_PHASE_2
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : Formosa 1 Phase 2
YEAR : 2019
SCOPE : Offshore Wind Farm
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
2020
UXO Clearance UK
Formosa
> TRACK_RECORD // 2020_FORMOSA_2
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : Formosa 2
YEAR : 2020
SCOPE : Offshore Wind Farm
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
2021
Hollandse Kust Zuid
> TRACK_RECORD // 2021_HOLLANDSE_KUST_ZUID
// OFFSHORE_WIND_INSTALLATION
---------------------------------------
PROJECT : Hollandse Kust Zuid
YEAR : 2021
SCOPE : Offshore Wind Farm - 139 Monopiles
HARDWARE : DBBC
---------------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
UXO Clearance
2023
UXO Clearance UK
Boskalis USA
> PARTNER_DEPLOYMENT // BOSKALIS_US_CAMPAIGNS
// OFFSHORE_WIND_INSTALLATION
------------------------------
PROJECT : South Fork Wind
YEAR : 2023
SCOPE : Offshore Wind Farm - 13 Monopiles
HARDWARE : Double Big Bubble Curtain
STATUS : COMPLETED // DEPLOYMENT VERIFIED
------------------------------
PROJECT : Revolution Wind
YEAR : 2024-2025
SCOPE : Offshore Wind Farm - 65 Monopiles
HARDWARE : Double Big Bubble Curtain
STATUS : COMPLETED // CAMPAIGN VERIFIED
------------------------------
PROJECT : Sunrise Wind
YEAR : 2025-2026
SCOPE : Offshore Wind Farm - 84 Monopiles
HARDWARE : Double Big Bubble Curtain
STATUS : DEPLOYMENT ACTIVE // CAMPAIGN VERIFIED
------------------------------
CLIENT : Boskalis
REGION : United States (East Coast)
2023 -
2026
TCP Phase II
> TRACK_RECORD // 2024_2025_TPC_PHASE_II
// ELECTRIFIED_OFFSHORE_SPREAD
--------------------------------
PROJECT : TPC Phase II Offshore Wind Farm
YEAR : 2024-2025
SCOPE : Offshore Wind Farm - 31 Jacket Foundations
HARDWARE : Double Big Bubble Curtain, 50% with Electrified Compressors
--------------------------------
STATUS: DEPLOYMENT ACTIVE // LOW-EMISSION FLOW
2024
UXO Clearance
Vineyard Wind
> TRACK_RECORD // 2024_VINEYARD_WIND_1
// OFFSHORE_WIND_INSTALLATION
--------------------------------
PROJECT : Vineyard Wind 1
YEAR : 2024 (1 month)
SCOPE : Offshore Wind Farm
HARDWARE : Big Bubble Curtain
--------------------------------
STATUS: COMPLETED // DEPLOYMENT VERIFIED
2027
"With our successful track record of development, construction and application of noise mitigation systems you can rely on our commitment to execute efficient, safe and reliable operations."

Bernhard Weyres, Founder & CEO